Follow along as Ed Miller reports on the reconstruction and restoration efforts at Eagle Bluff Lighthouse. From the first day the crew was onsite up to the most recent work being done, Ed has done a terrific job of chronicling the progress.
Feel free to leave a comment, if you would like!
May 14, 2024 Greetings! Turns out the guys were not there yesterday when I was there at 3 pm because they ran out of primer and had to go to […]
Read MoreMay 13, 2024 Greetings! When I got there about 2:30 this afternoon the National Restoration guys were not there. Maybe they were taking a break because some tools and paint […]
Read MoreMay 10, 2024 Greetings! Wednesday the tower was power washed. Looks really good. Thursday Josh and Dion started sanding paint off shutters. John Fletcher was on site in the afternoon. […]
Read MoreMay 7, 2024 Greetings! It was an exciting morning at EBLS. When I arrived the lantern and railing had been coated with primer. Josh and Dion were working on priming […]
Read MoreMay 2, 2024 Greetings! We started the long awaited restoration work at Eagle Bluff Light Station. We actually took a first step April 11 when our electrical contractor drilled a […]
Read More- « Previous
- 1
- …
- 3
- 4
- 5