June 19, 2024
June 19, 2024 Greetings! Work continued today on chimney brick and mortar repair and more prep work in the shutters to get them ready for the green paint. The lighthouse […]
June 19, 2024 Greetings! Work continued today on chimney brick and mortar repair and more prep work in the shutters to get them ready for the green paint. The lighthouse […]
June 18, 2024 Greetings! Today’s work was brick and mortar repairs on the chimney and more sanding of shutters to prep them for new paint. Also, the crew was working
June 17, 2024 Greetings! Today’s work was removing paint from the east window shutters. There is punky wood at the top of some of the shutters. That might mean having
June 13, 2024 Greetings! Josh and Dion wrapped up another week of work. Thursday they did more painting inside the lantern and it was back to brick and mortar repairs
June 12, 2024 Greetings! There are three days of pictures in this update. Prep for painting seemed to be the order of the day for June 10 and June 11.
June 6, 2024 Greetings! On Wednesday June 5, the crew was painting inside the lantern room. They completed all the glass installation the day before. On Thursday June 6, they
June 4, 2024 Greetings! I was not at EBLS yesterday because we had a lighthouse committee meeting and then it rained later in the afternoon, so I didn’t take any
May 30, 2024 Greetings! Most of the rear gable has been painted the lead color. If you look at the pictures you will see something missing. The dry rot on
May 29, 2024 Greetings! Yesterday was spending prepping for painting. When I arrived today at about 3:30 the underside of the south roof overhang had been painted lead color. The
May 23, 2024 Greetings! I got to EBLS about 2:15 today. Three pairs of painted shutters were put back on late yesterday. The green really looks good. So much better