Today was one of those days with the devil in the details when Mike and Billy were installing roof trim.
Chuck painted the trim on the small summer kitchen windows green. The windows came with the trim attached when they were installed. That is why we did not paint the trim for those windows ahead of time.

Mike and Billy installed rafters around the chimney that had to wait until the chimney was built.
Frankie continues to work on wiring in the barn.

It was exciting to see the first louver panel for the barn cupola.
Josh and Deion were working inside the tower. They did some final sanding before painting the inside of the tower wall. It should get a second coat of paint tomorrow.