From the Keeper’s Desk – May 12
Work on the barn at Eagle Bluff Light Station continues. The second floor was completed today. Painting continues inside the keeper’s residence.
From the Keeper’s Desk – May 12 Read More »
Work on the barn at Eagle Bluff Light Station continues. The second floor was completed today. Painting continues inside the keeper’s residence.
From the Keeper’s Desk – May 12 Read More »
Greetings! Work continues to move along steadily at Eagle Bluff Light Station. The painting crew is making excellent headway, and the first-floor bedroom is really starting to shine. Over in
From the Keeper’s Desk – May 8 Read More »
Greetings! Restoration efforts are moving along steadily at Eagle Bluff Light Station. Painting on the second floor is now complete, with the hallway fully finished and looking fantastic. Beth is
From the Keeper’s Desk – May 7 Read More »
Greetings! It was a productive day at Eagle Bluff Light Station, with progress taking place both inside the lighthouse and out on the grounds. Indoors, our painting crew continued their
From the Keeper’s Desk – May 6 Read More »
Greetings! April 29 and 30 were a couple of interesting days at Eagle Bluff Light Station. Late Monday a storm moved along the bay and up the west shore of
From the Keeper’s Desk – April 29 & 30 Read More »
Greetings! This morning’s focus was on painting and carpentry, both inside and out at the Eagle Bluff Light Station. Jeanne and Bob spent the morning prepping the office/music room for
From the Keeper’s Desk – April 28 Read More »
Greetings! Chuck made my work with this episode of From the Keeper’s Desk easy when he provided the following narrative: Many hands make light work! Ed, Sandy, Chuck, Laurie and
From the Keeper’s Desk – April 27 Read More »
On Tuesday, concrete work for a barn and summer kitchen was completed, including pouring floor slabs and stamping to create a wood plank appearance. By Wednesday, control joints were cut into the slabs to manage potential cracks due to temperature and moisture changes. Framing for the summer kitchen begins next Monday.
From the Keeper’s Desk – April 24 Read More »
The winter kitchen’s wainscoting issues have been resolved after uncovering serious problems. Laaksonen Builders, led by Mike, provided expert assistance. After a material delay, they sourced beadboard from Menards quickly, enabling the installation by Wednesday morning. The kitchen is now ready for visitors, while painters progress in adjacent areas.
From the Keeper’s Desk – April 23 Read More »
The lighthouse restoration is progressing, but significant damage was discovered in the winter kitchen’s wainscoting due to moisture issues. Initiating repairs, all affected wainscoting will be removed to prevent further damage. Meanwhile, work on the barn and summer kitchen continues with installation of insulation and preparations for pouring the foundation slabs.
From the Keeper’s Desk – April 18-21 Read More »