From the Keeper’s Desk – April 16

Today, significant improvements occurred at the lighthouse and surrounding areas. The barn and summer kitchen foundations were backfilled, and tree stumps removed. Inside, painting is brightening the winter kitchen and dining room. Upcoming tasks include electrical work and slab pouring, with construction led by Mike Laaksonen. Great job by everyone involved!

From the Keeper’s Desk – April 16 Read More »

From the Keeper’s Desk – April 11

The foundation walls for the barn and summer kitchen have been completed, with insulation installed afterward. Fitzgerald Construction will backfill next week, followed by conduit placement for plumbing. The floor is anticipated to be poured the Monday after Easter, with framing beginning shortly thereafter. Acknowledgments were given to the team and architect.

From the Keeper’s Desk – April 11 Read More »